Korean projects completed!

At the end of July, the last caissons were produced for our projects in Pohang and Ulsan. In Pohang, our skidding system was used to transfer caissons to the floating dock. In Ulsan, both our gantry slipform- and skidding system were used to construct and transfer the caissons.


Client: DL E&C
Project start date: Mars 2021
30 Nos Caissons
Caisson Size: W:32,5 L:34-40 H:18-28
Caisson Weight: 8-16000 ton
Project end date: 2024-07-30


Client: Namkwang E&C
Project start date: Augusti 2022
22 Nos Caissons
Caisson Size: W:23,5 L:42 H:25
Caisson Weight: 15000 ton
Project end date: 2024-07-30

After the final caissons we reflected at these projects, that started before the pandemic, and the resilience we had to capture to prevail, and ensure a success. Now the time has come to summarize and closure.
We thank our clients NAMKWANG E&C and DL E&C for the successful collaboration!