Caisson, Donghae, KoreaWe are almost finished with our breakwater project in Donghae, Korea!
20 out of 22 total caissons are now slipformed. On June 22, the final caisson is expected to be transfered to floating dock by our IP-CCV-system.

Client: POSCO E&C