In Singapore, the Tuas Finger 3 project is in full swing after a few short interruptions due to the covid situation.
Some speed facts:
- The latest caisson have been slipformed at a speed of 8.4 m per day.
- The transfer of the completed caissons has been carried out at an average speed of approximately 17 m per hour.
127 caissons have now been completed in Singapore – 100 are left to slide!
Read more about the project here.
Client: HDEC