Project update: Incheon New Port

We are now airborne in Incheon! Last week, the assembly work of our equipment had reached the point of lifting the slipform truss. Next step is to assemble the slipform and make our skidding equipment ready to start moving the base slab.

Project: Incheon New Port 1-2 Caisson Project
Scope of Supply: Slipform and transfer equipment
Qty: 42 Nos caissons
Weight: 11,000 tons
Dimension:  24,9x43x26,7 (WxLxH)
Client: Hyundai E&C Co., Ltd