Project Update: Laayoune Project

For Bygging-Uddemann’s Gantry Slipform and IP-CCV Transfer system, caisson production site layout can be adjusted as per project specifications. For Laayoune project, there are two stations after the gantry step which allows our client to perform additional works in two steps before load-out to floating dock. This picture was taken just upon completion of 2nd caisson.

Laayoune Project
Scope of work: Gantry Slipform and Transfer
Caisson size: 24 x 39 x 25 m
Caisson weight: approx 8 900 tons
Total number of caissons: 41 Nos
Client: Achirodon Group NV