Project Update: Tuas Terminal Phase 2 (Finger 3)

The construction of Singapore’s mega port in Tuas – planned to be the largest container terminal in the world – has reached a new milestone!
Caisson production for the third phase has just ended with the 227th caisson being completed in our gantry slipform station and transferred to the floating dock using our IP-CCV skidding system. In total, we have produced 539 caissons (91 + 221 + 227) for the project!

The Mega port project will continue with more phases (fingers) – we are ready to contribute with our technology when it is time!

Read about our systems for serial production here!

Project info:

Project: Tuas Terminal Phase 2 (Finger 3)
Scope of Supply: Slipform and skidding equipment
Qty: 227 Nos caissons
Weight: 13,800 tons
Dimension:  29x41x30 m (WxLxH)
Client: Joint Venture: Hyundai E&C Co., Ltd / Penta Ocean / Boskalis