Caisson production for the third phase has just ended with the 227th caisson being completed in our gantry slipform station and transferred to the floating dock using our IP-CCV skidding system. In total, we have produced 539 caissons (91 + 221 + 227) for the project!
The Mega port project will continue with more phases (fingers) – we are ready to contribute with our technology when it is time!
Read about our systems for serial production here!
Project info:
Project: Tuas Terminal Phase 2 (Finger 3)
Scope of Supply: Slipform and skidding equipment
Qty: 227 Nos caissons
Weight: 13,800 tons
Dimension: 29x41x30 m (WxLxH)
Client: Joint Venture: Hyundai E&C Co., Ltd / Penta Ocean / Boskalis